UpdateThis week’s major 35th floor slab pour has been re-scheduled AGAIN for Wednesday May 8. Unexpected progress on Tuesday, May 7 led to a revised schedule for the concrete pour. The decision was made at the end of the workday on Tuesday.

The concrete pour on May 8 will begin shortly after 7 AM and continue throughout the afternoon. Concrete finishing is expected to continue into the evening possibly as late as 11 pm or Midnight; though every effort will be made, within construction and safety standards, to complete the work as soon as possible.

Saturday Work May 11

Crews will be on site from 9 am.

General housekeeping work on site.

Interior drywall and suite work.

Installing railings.

Installing windows.

NOTE: Our next update will be posted on Monday, May 13.