Construction overview for Pier 27, week of May 21, 2019

Construction overview for Pier 27, week of May 21, 2019

This week at Pier 27 work will continue on the mechanical penthouse levels above the 35th floor. There will be ongoing forming and concrete work.  There will be deliveries to the site are through the week. Suites are being framed and drywalled from the podium levels...