This week at Pier 27 work will continue on the mechanical penthouse levels above the 35th floor. There will be ongoing forming and concrete work.
There will be deliveries to the site are through the week.
Suites are being framed and drywalled from the podium levels through the mid-20 floor levels.
Railing installation continues from the 16th floor and above. Window installation will continue above the 25th floor.
We will post updates this week when and if there are significant changes to the work schedule. We will also post an update on work planned for Saturday May 25 by Friday or sooner as scheduled work information is confirmed.