Saturday Work June 1

Crews will be on site from 9 am through the mid-afternoon.

They will be focussed on: 

  • General housekeeping work on site. 
  • Interior drywall work.
  • Suite layout work. 

NOTE: On Monday, June 3rd crews will be working in the generator room at 29 Queens Quay.  This will be taking place from 7:00 am to 3:00 pm. The contractors have assured us that there will be no disruptions to electrical service. 

This work is occurring under the shared services agreement between the development partners and the 29 Queens Quay condominium corporation.

* * * 

Our next construction update will be posted on Monday, June 3, 2019. 