Saturday Work + Look Ahead to the Week of July 29, 2019

Saturday Work + Look Ahead to the Week of July 29, 2019

by admin | Jul 26, 2019 | Uncategorized

Utilities Servicing Update GFL, the City of Toronto’s contractor for the utilities work (municipal sewer and water) has begun their work on Queens Quay at Freeland. They were not on site today, July 27. We await an update from them and hope to have more...
Utilities Work Monday July 22 & Saturday Work July 20

Utilities Work Monday July 22 & Saturday Work July 20

by admin | Jul 19, 2019 | Uncategorized

Utilities Servicing Update for Monday July 22, 2019 GFL, the City of Toronto’s contractor for the utilities work (municipal sewer and water) is expected to begin making cuts in the road on Monday. We expect this to have an impact on traffic in the vicinty of...
Pier 27 Construction & Utilities Servicing Update, July 15, 2019

Pier 27 Construction & Utilities Servicing Update, July 15, 2019

by admin | Jul 15, 2019 | Uncategorized

Construction & Utilities Servicing Update, July 15, 2019 GFL, the City of Toronto’s contractor for the utilities work (municipal sewer and water) was on-site today and has indicated work will now get underway on Wednesday. This essential work is required to...
Pier 27 Construction Update: Utilities work for Phase 3 to begin Monday, July 15

Pier 27 Construction Update: Utilities work for Phase 3 to begin Monday, July 15

by admin | Jul 12, 2019 | Uncategorized

July 12 Update: Utilities work to commence July 15, 2019 GFL, the contractor for the upcoming utilities work (municipal sewer and water) will begin work on Monday July 15, 2019. This essential work is required to connect municipal services to the Phase 3 tower at Pier...
Pier 27 Phase 3 Utilities Work & Look Ahead, July 11, 2019

Pier 27 Phase 3 Utilities Work & Look Ahead, July 11, 2019

by admin | Jul 11, 2019 | Uncategorized

UTILITIES (SEWER & WATER) WORK We have just received confirmation late this afternoon that utilities work is set to begin next week on Queen’s Quay. This work will connect Pier 27 Phase 3 to the City of Toronto’s sewer and water systems. The work will...
« Older Entries

Find Us

Address – Site Developers
56 The Esplanade #308, Toronto, ON M5E 1A7

About This Site

This site provided construction information for Cityzen Development Group & Fernbrook Homes’ Pier 27 15 Queens Quay from January 2018 through May 2020.

Search

July 2019
M T W T F S S
1234567
891011121314
15161718192021
22232425262728
293031  
« Jun   Aug »
  • Facebook
  • Twitter
  • Google
  • Instagram
  • RSS

Designed by Elegant Themes | Powered by WordPress