Midweek Phase 3 Update for Pier 27, August 21, 2019

Midweek Phase 3 Update for Pier 27, August 21, 2019

Phase 3 Work is progressing steadily at Pier 27 Phase 3: work continues on finsihing the exterior of the mechanical penthouse; windows arebeing completed on the 34th floor; corridor framing is being completed on the the 29th and 30th floors; suite framing is underway...
Look Ahead for the week of August 19, 2019

Look Ahead for the week of August 19, 2019

Phase 3 Work will continue this coming week on the mechanical penthouse. Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation.  Work on the west side the first floor, adjacent the parking...
Monday update for Pier 27 Phase 3, August 12, 2019

Monday update for Pier 27 Phase 3, August 12, 2019

Phase 3 Work contiunes on the mechanical penthouse this week as does interior work on the suites from the podium levels up through the top floors of the tower.  On Wednesday, August 14, work is scheduled to begin on the west side of the building to install the steel...