Midweek Update
Work on the mechanical penthouse continues for the balance of the week and will continue into next week.
Deliveries to the site are ongoing, bringing material and supplies for the interior work that is continuing from the 2nd floor through the 34th floor. Kitchens continue to installed and laundry equipment is beginning to be installed on the 2nd, 3rd and 4th floors. Suites are being framed and drywalled, with drywall work now reaching the 24th floor and above.
Window installation continues from the 34th floor and above.
Saturday Work August 10
Crews will be on site from 9 am.
General housekeeping work on site.
Interior drywall and suite work.
Installing windows.
Utilities Work
We are waiting for a full update from the City’s subcontractors GFL on the next phases of the utilities work. We will update this website and circulate the information once we have it.

NOTE: Our next update will be posted on August,12.