Phase 3

Work contiunes on the mechanical penthouse this week as does interior work on the suites from the podium levels up through the top floors of the tower. 

On Wednesday, August 14, work is scheduled to begin on the west side of the building to install the steel structure for the canopy. This work will occur adjacent the exisiting parking lot to the west of Pier 27. 

 

Utilities Work

On Wednesday, the contractors are set to begin laying water pipes along Queens Quay at Freeland and into the main road into Pier 27. There will disruptions to traffic access but the constractor will have flag cews on site to help direct vehicular and pedestrian traffic. We expect this phase of the work to continue for at least a week and possibly longer. 

We will provide an updated on August 14.