Midweek Update
Work on the mechanical penthouse is ongoing for the balance of the week and will continue into the week of August 19.
Deliveries to the site are ongoing, bringing material and supplies for the interior work that is continuing from the 2nd floor through the 34th floor. Kitchens continue to installed and laundry equipment is beginning to be installed on the on the first half of the podium. Suites are being framed and drywalled, with drywall work now reaching the from the upper podium and throughout the tower floors.
Balcony dividers have been installed to the 4th floor and this will continue through the next several weeks.
Saturday Work August 17
Crews will be on site from 9 am.
General housekeeping work on site.
Interior drywall and suite work.
Installing windows.
Utilities Work
Contractors GFL are underway with the utilities work this week. They will continue digging trenches and laying municipal water pipe through the week. Unfortunately, their necessary and required work is having an impact on traffic flow into Pier 27 and at Queens Quay East and Freeland. We ask for your patience and understanding.

NOTE: Our next update will be posted on August,16.