Phase 3

Work will continue this coming week on the mechanical penthouse. Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. 

Work on the west side the first floor, adjacent the parking lot, has been rescheduled to start this week. This will involve the installation of steel support beams for the canopy that will provide weather protection for the public realm.  

 

Utilities Work

GFL’s work on the installation of the municipal water pipe will continue throughout the week. There will be unavoidable traffic and pedestrian delays to ensure the safety of all. We ask for your understanding and patience as this essential work is underway.

Questions about construction progress?

Contact us at contact@pier27construction.info

We will post and circulate a midweek update on August 21. As always if there are significant changes to the construction schedule we will post and circulate them. 

Please check back regularly for updates or contact us