Phase 3

Work is progressing steadily at Pier 27 Phase 3:

  • work continues on finsihing the exterior of the mechanical penthouse;
  • windows arebeing completed on the 34th floor;

  • corridor framing is being completed on the the 29th and 30th floors;

  • suite framing is underway on the 22nd floor;

  • mechanical and electrical rough ins are underway on the 20th floor;

  • kitchen installations are underway on the 12th floor;

  • suites are being finished on the 3rd floor;

  • and the hoist (external service elevator) is operational to the 35th floor. 

 

Satruday Work
August 24

Crews are scheduled to be on-site from 9 am to work on the interiors of the podium and tower. There will also be general housekeeping work on the site. 

Questions about construction progress?

Contact us at contact@pier27construction.info

Our next shceduled post will be a lookahead for the week of August 26. As always if there are significant changes to the Saturday construction schedule we will post and circulate it. 

Please check back regularly for updates or contact us