Construction Update for Pier 27, September 25, 2019

Construction Update for Pier 27, September 25, 2019

Phase 3 Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. Drywall is being installed up to the 23rd floor. Suites are being framed and prepared for drywall installation from the 27th...
Construction Update, September 20, 2019

Construction Update, September 20, 2019

Phase 3 Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. Drywall is being installed up to the 23rd floor. Suites are being framed on the 34th floor. Suites are substantially finished...
Midweek Update, September 11, 2019

Midweek Update, September 11, 2019

Phase 3 Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. Suites are being framed on the 27th floor. Suites are substantially finished through the 8th floor of the podium Work on the...