Phase 3
Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. Drywall is being installed up to the 23rd floor. Suites are being framed and prepared for drywall installation from the 27th floor and above. Suites are substantially finished through the 9th floor of the podium
On the west and north sides of the building the steel support beams for the canopy have been installed, with the cross beams now installed on the north side.
Railings are being installed on the upper floors of the tower. Balcony dividers are being installed up to the 10th floor, with work on the 13th floor balconies about to begin. Balconies are being painted on the upper tower floors.
Saturday Work
Crews will be on site for the next two Saturdays, September 28 and October 5, from 9 am to work on the interiors and conduct general housekeeping work on site.
Utilities Work
GFL the City of Toronto’s contractor is now ‘dewatering’ the trenches they have dug for the water and sewer utilities. An onsite pump is draining excess water from these areas. We understand that GFL will restart active work on site as of Monday, September 30th. We will post updates on their work when we have them.






Our next construction update will be posted on October 4.
Please check back regularly for updates.