by admin | Oct 30, 2019 | Uncategorized
Phase 3 Work continues on the interiors of the building from the podium levels to the top floor of the building. Work on the mechanical penthouse cladding is progressing. Balcony divider installation is completed on the podium floors and is ongoing on the tower...
by admin | Oct 25, 2019 | Uncategorized
Phase 3 – Progress Update Mechanical Penthouse: Exterior cladding installation is now in progress 34th floor – Corridors walls framing in progress 32nd floor – suite layout 31st floor – suite framing 30th floor – self level flooring 29th to 27th floors –...
by admin | Oct 16, 2019 | Uncategorized
Utilities Work GFL is currently working on the watermain connection for Pier 27, Phase 3. The work is concentrated on Queens Quay and along the northern edge of the Phase 3 site. GFL expects the watermain work will continue for the next two weeks. They have partially...
by admin | Oct 11, 2019 | Uncategorized
Phase 3 & Utilities Work There will be general housekeeping work on site on Saturday, October 12th from 9 am through the afternoon. The site will be closed on Monday, October 14 for the Thanksgiving Holiday. Canopy construction The steel structure for the...
by admin | Oct 4, 2019 | Uncategorized
Phase 3 Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. Drywall is being installed in suites on the 24th floor, and is beginning to be installed on the in hallways on the 25th and 26th...