Midweek Update Pier 27 Phase 3, October 30, 2019

Midweek Update Pier 27 Phase 3, October 30, 2019

Phase 3  Work continues on the interiors of the building from the podium levels to the top floor of the building. Work on the mechanical penthouse cladding is progressing. Balcony divider installation is completed on the podium floors and is ongoing on the tower...
Pier 27 Phase Construction Update, October 25, 2019

Pier 27 Phase Construction Update, October 25, 2019

Phase 3 – Progress Update Mechanical Penthouse: Exterior cladding installation is now in progress 34th floor – Corridors walls framing in progress 32nd floor – suite layout 31st floor – suite framing 30th floor – self level flooring 29th to 27th floors –...
Pier 27 Construction Update, October 11, 2019

Pier 27 Construction Update, October 11, 2019

Phase 3 & Utilities Work There will be general housekeeping work on site on Saturday, October 12th from 9 am through the afternoon. The site will be closed on Monday, October 14 for the Thanksgiving Holiday.    Canopy construction The steel structure for the...
Construction update, October 4, 2019

Construction update, October 4, 2019

Phase 3 Interior work is progressing steadily throughout the podium and tower with drywalling, plumbing, kitchen and bathroom installation. Drywall is being installed in suites on the 24th floor, and is beginning to be installed on the in hallways on the 25th and 26th...