Phase 3 & Utilities Work

There will be general housekeeping work on site on Saturday, October 12th from 9 am through the afternoon. The site will be closed on Monday, October 14 for the Thanksgiving Holiday. 

 

Canopy construction

The steel structure for the canopy on the west and north face of the building is substantially complete. Finishing work that is being completed this week. 

Interior Work 34th Floor

The top floor of Phase 3 is being prepared for the next phase of work: framing and initial drywall installation. 

Interior Work 33rd Floor

Initial framing and insulation is being installed on the 33rd floor. 

Interior Work 28th Floor

Suite framing is complete on the 28th floor and suites are now having drywall installed. 

Parking Level Work

Beginning Tuesday, October 15, Parking Levels 1, 2 and 3 will have epoxy waterproofing applied. Work will begin the Parking Level 3. 

Balcony Glass

The glass for the balcony railings are now installed up to the 25th floor. In the coming weeks glass will be installed from the 26th through the 34th floors. 

Amenity Deck

Work is progressing on the 12th outdoor amenity deck. With the pergola now complete. Work on the outdoor pool is expected to be underway in the coming weeks. 

Balcony Dividers

Balcony dividers have been installed through to the 11th floor.  In the coming weeks dividers will be installed on the tower levels. 

Mechanical Penthouse

Louvers will cover the blue waterproofing ‘skin’ currently visible on the top of the building. Deliveries of the louvers are expected on October 11 and/or October 15. The louvers will be raised to the roof via the hoists (external elevators). They will be installed in the coming weeks. 

GFL Utilities Work

GFL is currently working Queens Quay East digging the space that new water main will occupy. This complex work as there is a lot of existing underground infrastructure under Queens Quay.  

Utilities work timeline

We have been advised that GFL expects their work to continue through the end of the year. We will have updates on this next week. 

Next Update

Our next scheduled update will be Wednesday, October 16. As always, we will post updates more frequently if there are changes to construction schedule. 

Sign Up for our Updates