Pier 27 Phase Construction Update, October 25, 2019

Pier 27 Phase Construction Update, October 25, 2019

Phase 3 – Progress Update Mechanical Penthouse: Exterior cladding installation is now in progress 34th floor – Corridors walls framing in progress 32nd floor – suite layout 31st floor – suite framing 30th floor – self level flooring 29th to 27th floors –...