Phase 3 

Work continues on the interiors of the building from the podium levels to the top floor of the building. Work on the mechanical penthouse cladding is progressing. Balcony divider installation is completed on the podium floors and is ongoing on the tower floors. The final stages of work on the parking garage levels is underway, as the sealing and waterproofing is now complete. As we noted last week, the completion of the roundabout for 29 Queens Quay and the start of paving work on the Phase 3 roundabout has been delayed due to supplier issues. 

We will have a full progress report update next week on November 6.

Saturday Work

Crews will be on site this Saturday, November 2, from 9 am to work on the interiors and conduct general housekeeping work on site.  

Utilities Work

GFL is working around the rainfall and given the forecast for Halloween we assume their work will be postponed for the day. Their work remains focussed on installing the water main connection for Phase 3 and is concentrated on Queens Quay and along the northern edge of the Phase 3 site. GFL expects this phase of the water main work will continue for the next 2 weeks. 

Questions about construction progress?

Contact us at contact@pier27construction.info

* * *

We will post and circulate our next update on Tuesday, November 5. As always if there are updates or significant changes to the construction schedule we will post and circulate them. 

Please check back regularly for updates or contact us