by admin | Dec 23, 2019 | Uncategorized
Phase 3 Crews will be working a partial day on Christmas Eve. Crews will also be on site through the holidays every day except for the statutory holidays of Christmas Day, Boxing Day and New Year’s Day. Between now and January 6, 2020, work will be focussed on...
by admin | Dec 20, 2019 | Uncategorized
Utilities Work GFL completed their work on the utilities today, Friday, December 20. Saturday There will be work on site on Saturday, December 21, from 9 am through the afternoon. This will involve general housekeeping on site, moving materials around the site and...
by admin | Dec 16, 2019 | Uncategorized
Please join us Monday, January 13, 2020 for updates on: Upcoming Minor Variance Application, reducing the number of parking spaces in the new tower. Construction outlook for Q1 & Q2 2020. The Meeting will take place at 29 Queens Quay East in the Main Floor Party...
by admin | Dec 12, 2019 | Uncategorized
Phase 3 & Utilities Work GFL Utilities Current Work GFL continues its work on the sanitary sewer connection for Phase 3 through this week and next. We expect they will continue their necessary lane occupation on the main access driveway until the work is...
by admin | Dec 10, 2019 | Uncategorized
As interior work progresses in the Phase 3 Tower at Pier 27, alarms within the building are being tested. While it is unlikely that adjacent residents will be bothered by this testing, we want to assure you that nothing is amiss and if you have heard or do hear alarms...