Construction Update for Pier 27, Phase 3, December 12, 2019

Construction Update for Pier 27, Phase 3, December 12, 2019

by admin | Dec 12, 2019 | Uncategorized

Phase 3 & Utilities Work   GFL Utilities Current Work GFL continues its work on the sanitary sewer connection for Phase 3 through this week and next. We expect they will continue their necessary lane occupation on the main access driveway until the work is...

Find Us

Address – Site Developers
56 The Esplanade #308, Toronto, ON M5E 1A7

About This Site

This site provided construction information for Cityzen Development Group & Fernbrook Homes’ Pier 27 15 Queens Quay from January 2018 through May 2020.

Search

December 2019
M T W T F S S
 1
2345678
9101112131415
16171819202122
23242526272829
3031  
« Nov   Jan »
  • Facebook
  • Twitter
  • Google
  • Instagram
  • RSS

Designed by Elegant Themes | Powered by WordPress