Utilities Work

GFL completed their work on the utilities today, Friday, December 20. 

Saturday

There will be work on site on Saturday, December 21, from 9 am through the afternoon. This will involve general housekeeping on site, moving materials around the site and ongoing suite finishing work in the interior of the building. 

NEXT WEEK:

Crews will be on site Monday, December 23 and for a partial day on Christmas Eve. 

We will have one more update and look ahead next week before taking a holiday break.