Phase 3
Crews will be working a partial day on Christmas Eve. Crews will also be on site through the holidays every day except for the statutory holidays of Christmas Day, Boxing Day and New Year’s Day.
Between now and January 6, 2020, work will be focussed on three (3) areas:
- The mechanical penthouse.
- Suite finishing on the upper podium and tower floors.
- Landscaping: specifically preparing the ground for paving and laying pavers.
Saturday Work
Staff will be on site Saturday, December 28, from 9 am to work on the interiors and conduct general housekeeping work on site.
Landscaping
Work is underway laying pavers at the entrance to the Phase 3 parking garage. Work will continue from now through the end of Janaury to prepare and lay pavers from the southern edge of the Phase 3 site, bordering 29 Queens Quay East, up the loacation of the hoist (external elevator) platform.

January 13, 2020
Community Meeting
Just a reminder that we hope to see residents of 39 and 29 Queens Quay East at the January 13, Community Update Meeting where the development team will be reviewing the upcoming Parking Variance for Phase 3 and the construction outlook for Q1 and Q2 2020.
For more info please click here.



We will post our next update in the New Year. As always if there are significant changes to the construction schedule we will post and circulate them.
Please check back regularly for updates or contact us.