Pier 27 Construction Update, December 6, 2019

Pier 27 Construction Update, December 6, 2019

Phase 3 The snow fall at the beginning of the week, and the snow forecast for this morning, will slow or prevent exterior work. Being weather-independent,  interior work is continuing steadily throughout the podium and tower with suites substantially completed to the...
GFL Update for Pier 27, December 3, 2019

GFL Update for Pier 27, December 3, 2019

We have updated information from the utilities contractors, GFL:  They advise that tonight will be the last night shift and the last day for their 24/7 emergency operation. They are completing the water-main connection this evening. GFL will be back to normal hours...
Update: Utilities Work & Pier 27 Phase 3 Construction

Update: Utilities Work & Pier 27 Phase 3 Construction

Updated: Utilities Work November 25 – December 3   24-hour work on Queens Quay 11/25 - 12/3 GFL, the contractors for the utilities work, have been given a permit by the City of Toronto to work 24 hours per day from November 11 through December 1 (and possibly...
Midweek Construction Update, November 13, 2019

Midweek Construction Update, November 13, 2019

Phase 3 Interior work is progressing steadily throughout the podium and tower with suites substantially completed through the podium. The interior amenity areas continue to get closer to their finished form, with work on the ceilings and floors underway.  Balcony...