Phase 3 Update

 

GFL Utilities Current Work

GFL crews have been on site backfilling areas that were dug out for the completetion of the sanitary sewer work in December. That work is now completed and both the municipal water and sewer connections are connected to the Phase 3 tower. 

Saturday Work January 12

There will be on-site deliveries, interior work and general site housekeeping from 9 am on Saturday through the afternoon. 

Ramp Work

Crews are currently working on the surfacing for the Phase 3 parking garage entrance ramp and this will continue through the balance of the month. 

 

Mechanical Penthouse

Crews are working on completing the cladding on the Mechanical Penthouse’s south wall this week and it is experience.

Landscaping

Initial work is underway on the hard surface landscaping. This will continue through January and February. 

 

Community Meeting Reminder!

REMINDER — Please join us this coming Monday,
January 13, 2020 for updates on:

  • Upcoming Minor Variance Application, reducing the number of parking spaces in the new tower.
  • Construction outlook for Q1 & Q2 2020.

The Meeting will take place at 29 Queens Quay East in the Main Floor Party Room.

All residents of 29 and 39 Queens Quay East are invited to attend. 

The meeting is hosted by Cityzen Development Group and members of the development team will be on hand to provide information and take questions. 

Please click on the link to download a printable PDF flyer for the meeting:
Pier 27 Development-Jan-13:20-Community Update Meeting

Date: January 13, 2020

Time: 7:00 pm – 8:30 pm

Location29 Queens Quay East, Main Floor Party Room