GFL Roadway Widening & Clean Cap Fill

GFL’s work east of the driveway will continue into early next week. The driveway work has been completed as has the work on excavating and filling to the west of the driveway along the northern edge of 15 Queens Quay East. Between now and January 6, 2020, work will be focussed on three (3) areas: 

Phase 3

Crews are continuing to work on completing the cladding installation on the mechanical penthouse. Work is also ongoing on the ground floor facade of 15 Queens Quay East. 

Between now and next week work will be focussed on three (4) areas: 

  1. Completing the mechanical penthouse exterior.
  2. Suite finishing on the upper podium and tower floors.
  3. Hard surface landscaping.
  4. The ground floor exterior of 15 Queens Quay East.

Saturday Work

Staff will be on site Saturday, February 1, from 9 am to work on the interiors and conduct general housekeeping work on site.  

Landscaping

Work is continuing on the installation of pavers along the eastern edge of 15 Queens Quay and the roundabout driveway access for 29 Queens Quay East and 15 Queens Quay East. 

Questions about construction progress?

Contact us at contact@pier27construction.info

We will post our next update on February 5. As always if there are significant changes to the construction schedule we will post and circulate them. 

Please check back regularly for updates.