Construction progress at 15 Queens Quay has been moving ahead steadily.

  • External cladding for the ground floor has been underway over the past weeks and is close to completion. 
  • Drywalling is complete up to the 32nd floor, close to completion on the 33rd floors and the 34th floor.
  • Kitchens are now installed up to the 32nd floor
  • Countertops are complete in all units up to the 30th floor
  • Plumbing is finished in all units up to the 17th floor.
  • Balcony dividers have been installed up to the 33rd floor and will soon be installed on the 34th.
  • Balcony railings are complete to the 34th floor. 

Looking Ahead

  • As a reminder: the removal of the hoist–external construction elevator–will begin on February 24 and is expected to take two weeks to complete.
  • Following the removal of the hoist, work on the units adjacent to the hoist will begin. 
  • The corner cladding for the Mechanical Penthouse is expected to be complete by or before March 17
  • The 29 QQE and 15 QQE Roundabout is expected to be completed by March 17.

We will have an update next week. Please check back regularly.