Focus of work at 15 Queens Quay for the coming week:

  • Balcony railings are being installed on the sections of the balconies that were adjacent the hoist. This work is ongoing for the coming week. 
  • Landscaping work is continuing on the site: interlock pavers are being laid at the southeast side of the site, adjacent the tower.
  • Suite inspections are continuing on the 7th and 8th floors. 
  •  Suite closing/move-ins continue on the 5th floor.
  •  Suite finishing is ongoing above the 13th floor.
  •  Finishing of the “hoist suites” is progressing with installing baseboard and tiles through next week. 

We note that work may progress at a slower pace in order to ensure that physical distancing is maintained. 

Saturday Work

Staff will be on site Saturday,  April 11 and Saturday April 18, from 9 am. They will be installing railings in areas of the balconies that were adjacent to the hoist, and to conduct general housekeeping work on site.  

Questions about construction progress?