Project Update for 15 Queens Quay:
-
Work on the right of way adjacent the Sales Centre is scheduled to be completed by end of day April 24.
15 Queens Quay Project Look Ahead
-
Mechanical penthouse: finishing the exterior by installing metal panels on the corners; estimated target date for completion is the end of next week.
-
34th floor to the 13th floor: interior finishes as required.
-
Hoist suites – 2nd floor to 34th floor: interior finishes ongoing.
-
Hoist suite balcony railings: ongoing; targeted to be complete by the end of next week.
-
Ground floor landscape – concrete removal ongoing.
We note that work may progress at a slower pace in order to ensure that physical distancing is maintained.
Saturday, May 2
- Staff will be on site Saturday, May 2, from 9 am. They will be installing railings in areas of the balconies that were adjacent to the hoist, and to conduct general housekeeping work on site.

Landscape work at 15 Queens Quay
Work on the hardscape landscaping will continue through next week and into next month, on the east side of 15 Queens Quay East.
All work on site is being conducted according to
Provincial Guidelines.
Hand-washing and physical distancing
practices are in place.