Phase 3 Construction overview October 15 – 20, 2018

Phase 3 Tower overview for the week This week work concrete will be completed on the the 17th floor of the Phase 3 tower and begin on the 18th floor. A mix of internal and external work will occur on the lower floors, with concrete work focussed on completing the vertical columns from the 17th to the 18th floor at the beginning of the week. Most of the week will involve preparing for and executing the slab pour for the 18th floor.  This week’s major concrete pour is scheduled for Friday, October 19. It is likely that the critical work Read More

Saturday work October 13, 2018

Work on site Saturday from 9 AM There will be work this Saturday, Saturday October 13, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include: Grinding Window installation Form cracking–i.e. separating wooden forms to prepare them for use in next week’s concrete work. General site housekeeping Our overview of next week’s schedule will be posted by or before 7 am, Monday, October 15.

Phase 3 Construction overview October 9 – 13, 2018

Phase 3 Tower overview for the week  This week work concrete will continue on the the 17th floor of the Phase 3 tower. A mix of internal and external work will occur on the lower floors, with concrete work focussed on preparing for and executing the slab pour for the 17th floor.  This week’s major concrete pour is scheduled for Thursday, October 11. It is likely that the critical work of concrete finishing will run late into the evening however every effort will be made to finish the work as early as possible. We expect work onsite for Saturday, October Read More

Saturday work October 6, 2018

Work on site Saturday from 9 AM There will be work this Saturday, Saturday October 6, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include: Grinding Window installation General site housekeeping Our overview of next week’s schedule will be posted by or before 7 am, Tuesday, October 9.

Monday concrete pour cancelled rescheduled for Tuesday, October 2.

Concrete pour moved to Tuesday, October 1 The concrete pour scheduled for today, Monday, October 1, has been cancelled due to rain. It is now scheduled for Tuesday, October 2.  It is expected that the concrete pour and concrete finishing will run late into the evening. Every effort will be made to complete the work as early as possibly. However, in order to ensure the structural integrity of the building, continuous concrete pours cannot be interrupted. As well the City of Toronto Construction Noise By-Law permits concrete pours to continue outside standard (e.g. after 7 pm) work hours. For more Read More

Phase 3 Construction overview October 1 – 5, 2018 – Updated

Phase 3 Tower overview for the week – UPDATED This week work will reach the 17th floor of the Phase 3 tower. A mix of internal and external work will occur on the lower floors, with concrete work focussed on the 16th floor and the initial columns to the 17th floor. The major concrete pour scheduled for Monday, October 1, has been cancelled due to rain and is now scheduled for Tuesday, October 2. It is likely that may run late into the evening however every effort will be made to finish the work as early as possible. If there Read More

Saturday work September 29 & Concrete Pour October 1

Work on site Saturday from 9 AM There will be work this Saturday, September 22, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include: Grinding Window installation General site housekeeping Our overview of next week’s schedule will be posted by or before 7 am, Monday, October 1. Concrete Pour, Monday October 1 The 16th floor slab concrete pour is scheduled for Monday, October 1st. Pouring and finishing work is expected to go late. Finishing for 15th floor pour on September 21st went through the night due to weather conditions. It is hoped Read More

Phase 3 Construction overview September 24 – 28, 2018

Phase 3 Tower overview for the week This week work will reach the 16th floor of the Phase 3 tower. A mix of internal and external work will occur on the lower floors, with concrete work focussed on the 15th and 16th floors.  We will update this site later in the week if we have information on late evening concrete work. Please check back for updates.  Detail of tower work this week 2nd Floor Stairwells/shafts/garbage chutes Install risers and garbage chutes Install outside wall track/corridor track Layout of corridor and mock-up suites 3rd Floor Install risers and garbage chutes 5th Read More

Friday, September 21’s concrete pour to go late

Friday’s concrete pour may run till 11 pm We expect Friday’s scheduled concrete pour will continue into the evening, possibly as late as 11 pm.  As we note on this site (please click here), continuous concrete pours, which include the pouring and the finishing of the concrete, are permitted to continue past 7 pm on weekdays if and when necessary. This work is permitted to go late as any interruption in pouring and finishing of concrete would compromise the structural integrity of the building under construction.  Concrete truck on-site at Pier 27