Phase 3 Construction overview April 9 – 13, 2018

29 Queens Quay Garage Beginning Thursday, April 12, cleaning and painting  columns on the P3 and P4 parking levels will get underway. Parking spots 1 – 12 on Ps and P4 will be need to be cleared of cars for the duration of the work, which is expected to take up to 3 days. Construction management has been in touch with the property management at 29 Queens Quay to to arrange for alternative parking for the affected residents, for the duration of the work.  1-12 to be evacuated for 3 consecutive days. If you have questions about the alternative parking arrangements Read More

Updated: Phase 3 Construction Overview April 2 – 6, 2018

29 Queens Quay Parking Garage. Work continues again this week in the mechanical room of the 29 Queens Quay parking garage. It is expected that this work, will continue through Thursday, April 5.  Two supporting columns in the mechanical room are being reinforced to strengthen them, as they are under what will be the southern portion of the podium of the new Phase 3 Tower.  New concrete is being poured, the columns will then be finished, with the forming shown in this picture removed. Once completed, all work related to Phase 3 in the mechanical room will be  done.   NOTE: On Read More

Phase 3 Construction Overview Mar 26 – 29, 2018

UPDATE: scheduled to remove and reconstruct a section of concrete slab, at grade level, just west of the entrance to the 29 Queen’s Quay parking garage, was again rescheduled to the following week. 29 Queens Quay Parking Garage. Work continues this week in the mechanical room of the 29 Queens Quay parking garage. Two supporting columns in the mechanical room are being reinforced to strengthen them, as they are under what will be the southern portion of the podium of the new Phase 3 Tower. New concrete is being poured, the columns will then be finished, with the forming shown Read More

Phase 3 Construction Overview Mar 19 – 23, 2018

This week work  was scheduled to get underway to remove and reconstruct a section of concrete slab, at grade level, just west of the entrance to the 29 Queen’s Quay parking garage. However, this work is now scheduled to begin next week. Once the existing slab is removed, a new concrete slab will be poured in its place. This week will also see the installation of construction hoardings  and a protected walkway along Queen’s Quay, just north of the Phase 3 tower, is scheduled to start this week Concrete pours continue for the second, third and fourth floors: Second floor Read More

Phase 3 Construction Overview Mar 12 – 16, 2018

This week concrete pours continue for the second and third floors continue; and the first concrete pours for the fourth floor will begin week, such as: Second floor deck pours Monday through Friday. Third floor deck pours Monday and Tuesday. Vertical columns from the third floor to the fourth floor, Monday thru Wednesday. Work on the third floor slab, Wednesday thru Friday. Fourth deck pours Monday through Friday. There will also be work in the Phase 3 underground levels:  On level P1 there will be: Grinding, Installation of Light Fixtures, Installation of sprinkler pipes, and Wiring installation. On level P2 there will Read More

Phase 3 Construction Overview Mar 5 – 9, 2018

This week concrete pours for the third floor slab are scheduled to begin and continue through the week.  Concrete work will also continue in these areas: Remaining vertical columns from the ground floor to the second floor. Pouring mezzanine vertical columns to the 2nd floor. Continuing pouring the second floor vertical columns to the 3rd floor.