by admin | Jun 1, 2020 | Uncategorized
Home Key milestones for the remainder of spring and summer 2020 at Pier 27. Commercial parking has been consolidated in the north parking lot as of May. Move ins are occurring up to the 20th floor, and 75% occupancy approval was achieved in May. Painting balconies...
by admin | May 25, 2020 | Uncategorized
Municipal Servicing Work Continues in the right of way and on Queens Quay Contractor GFL will be working through this week and into early June to complete the necessary and permitted municipal servicing work. Once GFL has secured the final connections, they will...
by admin | May 19, 2020 | Uncategorized
Municipal Servicing Work Continues this week. Contractor GFL will be working again this week. Last week’s rain on Friday caused them to lose a day, so we expect this will add time to their work schedule this month. GFL is still working on the installation of two...
by admin | May 11, 2020 | Uncategorized
Municipal Servicing Work Continues Contractor GFL is continuing to work on completing municipal service installations. GFL is currently installing two water services in front of the sales centre pavilion. This work will be ongoing for the next 3 weeks until GFL can...
by admin | May 4, 2020 | Uncategorized
Municipal Servicing Work Continues Contractor GFL is continuing to work on completing municipal service installations. This week will see pipe installation work along the right of way on the north side of the site, just south of the existing sidewalk. Work hours this...
by admin | Apr 28, 2020 | Uncategorized
Contractor GFL is completing the remaining municipal service installations starting this week. Work hours will be between 7 a.m. to 5:30 p.m. Monday-Friday. The work program is approximately 4 weeks in duration. It will not impact the Pier 27 access driveway or the...