by admin | Apr 24, 2020 | Uncategorized
Project Update for 15 Queens Quay: Work on the right of way adjacent the Sales Centre is scheduled to be completed by end of day April 24. 15 Queens Quay Project Look Ahead Mechanical penthouse: finishing the exterior by installing metal panels on the corners;...
by admin | Apr 17, 2020 | Uncategorized
Project Update for 15 Queens Quay: Mechanical penthouse – finishing the exterior by installing metal panels on the corners is esitimated to finish by the end of this month (April) 34th floor to the 13th floor – interior finishes as required Hoist suites – 2nd floor to...
by admin | Apr 9, 2020 | Uncategorized
UPDATED April 16, 2020 Focus of work at 15 Queens Quay for the coming week: Balcony railings are being installed on the sections of the balconies that were adjacent the hoist. This work is ongoing for the coming week. Landscaping work is continuing on the site:...
by admin | Apr 6, 2020 | Uncategorized
Per the Province of Ontario’s April 3, 2020 update to the list of essential workplaces, construction work will continue to complete suites and landscaping at 15 Queens Quay East. We will post our next construction update midweek. List of essential workplaces ...
by admin | Apr 2, 2020 | Uncategorized
Pier 27 construction activity is adhering to social distancing while continuing to improve cleanliness and promoting personal hygiene routines for all our staff and contractors throughout the project. _______________________ Key Current Activities at 15 Queens Quay:...
by admin | Mar 27, 2020 | Uncategorized
Pier 27 construction activity is adhering to social distancing while continuing to improve cleanliness and promoting personal hygiene routines for all our staff and contractors throughout the project. _______________________ Key Current Activities: Landscaping is...