Phase 3 Construction overview May 7 – 11, 2018

Phase 3 Tower Construction Overview This week concrete work on the tower will progress to the fifth and sixth floors. This will include concrete pours for floor slabs and vertical columns. It is expected that all concrete work will be completed within normal weekday construction hours, that is between 7 am and 7 pm. If there is any requirement for later work we will post notifications in advance here and advise property management.    Work on the 29 Queens Quay roundabout Work to replace the concrete on the fenced off section  the 29 Queens Quay roundabout will continue this week. Read More

29 Queens Quay clean-up in P1 Garage – ongoing through next week

There remains some minor clean up work to do in the 29 Queens Quay garage on the P1 level. This work is scheduled to be completed by the end of next week, May 11. If there is any change to this schedule we will post it here.   We thank the Board of 29 Queens Quay for providing the pictures below which illustrate the area that will be addressed over the coming days.  If you have any questions please email us at contact@Pier27construction.info or if you are resident of 29 Queens Quay you may also contact Property Management via Jeff Stevenson at Jeff.Stevenson@fsresidential.com

Phase 3 Construction overview April 30 – May 4, 2018

This week work on the Phase 3 tower is focussed in three main areas: Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium.  Crews will be pouring concrete on floors four and five of the Phase 3 podium.  Flying formwork tables to the fourth and fifth floors. These are the wooden structures used to provide forms into which concrete is poured. 

Update work in 29 Queens Quay garage

UPDATE – April 24, 2018 Work in the 29 Queens Quay garage will be completed today, April 24, or at the latest tomorrow, April 25. Every effort is being made to ensure the safe and quick and completion of clean-up efforts. If you have any questions about this work please contact us at contact@Pier27construction.info or contact Property Management c/o Jeff Stevenson at Jeff.Stevenson@fsresidential.com

Phase 3 Construction overview April 23 – 27, 2018

Work at 29 Queens Quay This week subcontractors Mayfair will be working on P1 level of the 29 Queens Quay parking garage on Monday and Tuesday. This work will include the clean-up of parking spots.  Mayfair will also be working in the generator room next week.   Phase 3 Tower work This week work on the Phase 3 tower is focussed in three main areas: Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium.  Pouring concrete on floors four and five of the Phase 3 podium.  Flying formwork tables to the Read More

Concrete reconstruction work in the laneway at 29 Queens Quay

Construction site conditions and weather conditions have caused scheduled work on the concrete slab that is part of the 29 Queens Quay laneway roundabout. This section that has been fenced off to permit construction of the podium of the Phase 3 Tower, is scheduled to be removed and rebuilt. Our latest information is that this will begin Wednesday, April 17.  We will provide an update on specific scheduling as soon as the information is available. 

Phase 3 Construction overview April 16 – 20, 2018

29 Queens Quay garage work Mayfair Electric will be commencing work this week, April 16th – 20th , in the P1 garage at the North East corner, adjacent the area pictured on the right. This work will be focused on: Installing conduit in P1 at North face wall Installing conduit at ramp wall Installing pull box at ramp wall There will be traffic control in place during work in high traffic areas. Phase 3 Construction The main focus of work on the Phase 3 tower this week will be ongoing concrete pours on levels 3, 4, and 5. Slab pours and Read More

Phase 3 Construction overview April 9 – 13, 2018

29 Queens Quay Garage Beginning Thursday, April 12, cleaning and painting  columns on the P3 and P4 parking levels will get underway. Parking spots 1 – 12 on Ps and P4 will be need to be cleared of cars for the duration of the work, which is expected to take up to 3 days. Construction management has been in touch with the property management at 29 Queens Quay to to arrange for alternative parking for the affected residents, for the duration of the work.  1-12 to be evacuated for 3 consecutive days. If you have questions about the alternative parking arrangements Read More

Updated: Phase 3 Construction Overview April 2 – 6, 2018

29 Queens Quay Parking Garage. Work continues again this week in the mechanical room of the 29 Queens Quay parking garage. It is expected that this work, will continue through Thursday, April 5.  Two supporting columns in the mechanical room are being reinforced to strengthen them, as they are under what will be the southern portion of the podium of the new Phase 3 Tower.  New concrete is being poured, the columns will then be finished, with the forming shown in this picture removed. Once completed, all work related to Phase 3 in the mechanical room will be  done.   NOTE: On Read More