REMINDER: Monday, February 12  power shutdown at 29 Queens Quay 8 am to 10 pm

REMINDER: this Monday, February 12  power will be shut down in 29 Queens Quay from 8 am to 10 pm. This shut down is  necessary to enable the setup of the permanent power supply for the Pier 27 Phase 3 tower, 15 Queens Quay East. The construction management team apologizes for this inconvenience and has provided advance notice to your property manager, Board of Directors and through this website.  The electrical work that will be done during the temporary power shutdown is in compliance with the original Pier 27 electrical power delivery design. This permanent solution will replace the temporary Read More

Update: 29 Queen’s Quay P3 & P4 column work will finish Saturday Feb 10

The work column reinforcement that has been underway this week on the P3 and P4 levels at 29 Queens Quay will be completed on Saturday, February 10. To complete the work cews will be working on the P3 level until 8pm tonight, February 9th and will also be working tomorrow, February 10, from 7 am to 2 pm to finish the clean-up. The tenants who have been temporarily parking on P2 can reoccupy their parking sports by 3 pm tomorrow, Saturday February 10th. 

Phase 3 construction for February 4 – 11

Form the 4th through the 11th of February concrete work continues on the ground floor, mezzanine and second levels. As well column reinforcement is ongoing through the week in parking levels 3 and 4 at 29 Queens Quay as part of Phase 3’s construction process. Today and this week construction crews at the Phase 3 tower will be pouring concrete in the following areas: South mezzanine level Ground floor level Walls and columns from the ground floor to the second level Column reinforcement in the parking levels at 29 Queens Quay as part of the Phase 3 tower construction. REMINDER: Power will Read More

Column reinforcement in 29 Queens Quay Parking Garage February 2 – 10

Starting on Friday February 2nd column reinforcement work will commence in on the P3 and P4 levels of the Parking Garage of 29 Queens Quay. This work is a necessary part of the build out of the Phase 3 tower at Pier 27. Unfortunately this necessary work will be a short-term inconvenience for those in 29 Queens Quay who use parking spots 1 through 12 in the P3 and P4 levels, however alternative parking spots have been provided on the P2 level:   This will affect Parking Spaces 1 through 12 on the P3 and P4 levels. Cars in those spaces Read More

January 29 Construction Update for Pier 27 Phase 3

The Phase 3 tower at Pier 27 is visibly beginning to rise above grade with forming and concrete work underway on the ground floor, mezzanine and second levels. Today and this week construction crews at the Phase 3 tower will be pouring concrete in the following areas: South mezzanine level Ground floor level Walls and columns from the ground floor to the second level Please check back with us regularly for further updates.

Update + Next full construction post on Monday, January 29

Our next full construction update for Pier 27 will be posted on Monday, January 29, 2018.  Just to note that concrete work continues on the 2nd floor slab as well as pouring concrete for columns that will support the 3rd floor. Regarding the February 12 power shutdown:  The start time has been shifted to 8 am on Monday, February 12th in response to resident’s feedback. We also note that there may be some confusion regarding the Family Day Holiday, which is on Monday, February 19th, the 12th. There will be no site work on the 19th as it is a Read More

Construction update for the week of January 22, 2018

Work this week at the Pier 27 Phase 3 Tower will pick up from last week with more concrete pouring. Work will continue on the ground floor slabs. There will also be work to pour the ground verticals, the walls and columns of that rise from the ground floor. Work will also begin on the forming and decking of the mezzanine level; the level between ground and 2nd  floors. It is expected all work will be carried during normal construction hours between 7 am and 7 pm Monday to Friday. Work on the Pier 27 Phase 3 Tower. January 2018

Update re February 12 Electrical Work & 29 Queen’s Quay Power Shut Down

In response to feedback from resident, the construction management team has revised the start time of the necessary power shut down on February 12th. The power will now be shut off in 29 Queens Quay from 8 am to 10 pm. This shut down is necessary to enable the setup of the permanent power supply for the Pier 27 Phase 3 tower, 15 Queens Quay East. The construction management team apologizes for this inconvenience and is providing advance notice to ensure that residents of 29 Queens Quay may have adequate time to prepare. The electrical work that will be done during Read More