Phase 3 Construction overview May 28 – June 1, 2018

Phase 3 Tower This week work on the Phase 3 Tower will see the finishing the 7th floor concrete slab and work on the walls/columns that connect to the 8th floor Work will also begin on the forming of the 8th floor slab at south end of the podium.  Wooden forming panels will removed or be flown into position with the onsite cranes, as concrete work progesses.  Please check back for further updates. If you have questions about the progress of the construction please get in touch with us at contact@pier27construction.info 29 Queens Quay Roundabout Waterproofing work on the section of the 29 Queens Read More

Phase 3 Construction overview May 22 – 25, 2018

Phase 3 Tower This week work on the Phase 3 Tower will see the finishing the 6th floor concrete slab and work on the walls/columns that connect to the 7th floor Work will also begin on the forming of the 7th floor slab at south end of the podium.  Crews will also remove the steel piles along the ground floor at west side of the podium.  Please check back for further updates. If you have questions about the progress of the construction please get in touch with us at contact@pier27construction.info 29 Queens Quay Roundabout Work continues this week to waterproof the ground floor Read More

Phase 3 Construction overview May 14 – 18, 2018

Phase 3 Tower This week concrete work will proceed on the 5th and 6th levels of the podium. Both floor slab and vertical columns will be poured on the 5th level and on the the southern portion of the 6th level.  Wooden forming panels will be moved up a level as work is completed on the level under construction.  Please check back for further updates.  29 Queens Quay Roundabout The new concrete slab for the western portion of the 29 Queens Quay roundabout has been completed.  This week the slab will be waterproofed. It takes approximately 1 week for the Read More

Phase 3 Construction overview May 7 – 11, 2018

Phase 3 Tower Construction Overview This week concrete work on the tower will progress to the fifth and sixth floors. This will include concrete pours for floor slabs and vertical columns. It is expected that all concrete work will be completed within normal weekday construction hours, that is between 7 am and 7 pm. If there is any requirement for later work we will post notifications in advance here and advise property management.    Work on the 29 Queens Quay roundabout Work to replace the concrete on the fenced off section  the 29 Queens Quay roundabout will continue this week. Read More

29 Queens Quay clean-up in P1 Garage – ongoing through next week

There remains some minor clean up work to do in the 29 Queens Quay garage on the P1 level. This work is scheduled to be completed by the end of next week, May 11. If there is any change to this schedule we will post it here.   We thank the Board of 29 Queens Quay for providing the pictures below which illustrate the area that will be addressed over the coming days.  If you have any questions please email us at contact@Pier27construction.info or if you are resident of 29 Queens Quay you may also contact Property Management via Jeff Stevenson at Jeff.Stevenson@fsresidential.com

Phase 3 Construction overview April 30 – May 4, 2018

This week work on the Phase 3 tower is focussed in three main areas: Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium.  Crews will be pouring concrete on floors four and five of the Phase 3 podium.  Flying formwork tables to the fourth and fifth floors. These are the wooden structures used to provide forms into which concrete is poured. 

Update work in 29 Queens Quay garage

UPDATE – April 24, 2018 Work in the 29 Queens Quay garage will be completed today, April 24, or at the latest tomorrow, April 25. Every effort is being made to ensure the safe and quick and completion of clean-up efforts. If you have any questions about this work please contact us at contact@Pier27construction.info or contact Property Management c/o Jeff Stevenson at Jeff.Stevenson@fsresidential.com

Phase 3 Construction overview April 23 – 27, 2018

Work at 29 Queens Quay This week subcontractors Mayfair will be working on P1 level of the 29 Queens Quay parking garage on Monday and Tuesday. This work will include the clean-up of parking spots.  Mayfair will also be working in the generator room next week.   Phase 3 Tower work This week work on the Phase 3 tower is focussed in three main areas: Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium.  Pouring concrete on floors four and five of the Phase 3 podium.  Flying formwork tables to the Read More

Concrete reconstruction work in the laneway at 29 Queens Quay

Construction site conditions and weather conditions have caused scheduled work on the concrete slab that is part of the 29 Queens Quay laneway roundabout. This section that has been fenced off to permit construction of the podium of the Phase 3 Tower, is scheduled to be removed and rebuilt. Our latest information is that this will begin Wednesday, April 17.  We will provide an update on specific scheduling as soon as the information is available. 

Phase 3 Construction overview April 16 – 20, 2018

29 Queens Quay garage work Mayfair Electric will be commencing work this week, April 16th – 20th , in the P1 garage at the North East corner, adjacent the area pictured on the right. This work will be focused on: Installing conduit in P1 at North face wall Installing conduit at ramp wall Installing pull box at ramp wall There will be traffic control in place during work in high traffic areas. Phase 3 Construction The main focus of work on the Phase 3 tower this week will be ongoing concrete pours on levels 3, 4, and 5. Slab pours and Read More