Update re February 12 Electrical Work & 29 Queen’s Quay Power Shut Down

In response to feedback from resident, the construction management team has revised the start time of the necessary power shut down on February 12th. The power will now be shut off in 29 Queens Quay from 8 am to 10 pm. This shut down is necessary to enable the setup of the permanent power supply for the Pier 27 Phase 3 tower, 15 Queens Quay East. The construction management team apologizes for this inconvenience and is providing advance notice to ensure that residents of 29 Queens Quay may have adequate time to prepare. The electrical work that will be done during Read More

Electrical Work – Power Shut Down February 12

UPDATED On February 12th the power will be shut off in 29 Queens Quay for 14 hours, from 8 am to 10 pm. This shut down is necessary to enable the setup of the permanent power supply for the Pier 27 Phase 3 tower, 15 Queens Quay East. The construction management team apologizes for this inconvenience and is providing advance notice to ensure that residents of 29 Queens Quay may have adequate time to prepare.   The electrical work that will be done during the power outage will permit the establishment of the permanent power supply for the Phase 3 construction Read More

Construction update for the week of January 8, 2018

Work has resumed on the site of the Pier 27, Phase 3 tower following the Holiday break.  As of the end of year the Parking Level 1 of the tower was 95% complete and work was underway to begin the concrete pours for the ground floor slab and the vertical columns for the second floor of the tower. Highlights of upcoming construction work for the week of January 8, 2018: Over the coming week concrete pours will proceed for the ground floor slab and second floor vertical columns, as weather permits.  Concrete work is not expected to occur outside of Read More