Pier 27 – 15 Queens Quay Update, March 27, 2020

Pier 27 – 15 Queens Quay Update, March 27, 2020

Pier 27 construction activity is adhering to social distancing while continuing to improve cleanliness and promoting personal hygiene routines for all our staff and contractors throughout the project.   _______________________ Key Current Activities: Landscaping is...
Friday Update for Pier 27 Construction, March 6, 2020

Friday Update for Pier 27 Construction, March 6, 2020

The 29 Queens Quay Roundabout has been handed over and is now basically operational.  The curbs and the unfinished interlocking pavers will be reinstated in early April. Temporary concrete has been placed in the areas where the old interlocking pavers to be removed....
Pier 27 15 Queens Quay Update, February 24, 2020

Pier 27 15 Queens Quay Update, February 24, 2020

Pier 27 15 Queens Quay Update As a reminder, the hoist (external construction elevator) at 15 Queens Quay will begin being removed on Monday February 24. It is expected this will take up to two weeks to be completed.   Ramp Work Crews are currently close to completing...
Weekend Update for Pier 27 – 15 Queens Quay

Weekend Update for Pier 27 – 15 Queens Quay

Saturday, February 22 Crews will be on site working on suite interiors from the 10th floor and up.  Crews will also be in to continue working on the main floor exterior cladding.  There will also be general housekeeping work on site.  Looking Ahead The removal of the...
Construction Update for Pier 27 – 15 Queens Quay

Construction Update for Pier 27 – 15 Queens Quay

Construction progress at 15 Queens Quay has been moving ahead steadily. External cladding for the ground floor has been underway over the past weeks and is close to completion.  Drywalling is complete up to the 32nd floor, close to completion on the 33rd floors and...