Electrical Work – Power Shut Down February 12

UPDATED On February 12th the power will be shut off in 29 Queens Quay for 14 hours, from 8 am to 10 pm. This shut down is necessary to enable the setup of the permanent power supply for the Pier 27 Phase 3 tower, 15 Queens Quay East. The construction management team...

Construction update for the week of January 8, 2018

Work has resumed on the site of the Pier 27, Phase 3 tower following the Holiday break.  As of the end of year the Parking Level 1 of the tower was 95% complete and work was underway to begin the concrete pours for the ground floor slab and the vertical columns for...