2020 Q1 and Q2 Construction Timeline (as of January 17, 2020)

December 16 – January 24: Completion of ramp to the 15 Queens Quay East underground garage.

December 16 – March 13: Completion of the pedestrian link to the Waterfront Toronto Parking Lot, on the west side of 15 Queens Quay East.

January 13 – January 29: Road widening excavation & clean cap, along the northern section of the site adjacent Queens Quay East.

January 17 – February 18: Reinstatement of Building D [29 Queens Quay East] Valet & Roundabout.

February 1 – February 4: Construction of the pedestrian walkway adjacent 15 Queens Quay East.

February 19 – February 28: Reinstatement of Building D [29 Queens Quay East] Fire Route.

February 24 – March 6: Hoist [External construction elevator] removal from 15 Queens Quay East.

March 6 – May 31st: Commencement of remaining 15 Queens Quay East landscape work.

Spring 2020 – end of May: Reinstatement of Building D [29 Queens Quay East] Softscape (e.g. plantings). 

Landscape Plan for Q1 and Q2 work at Pier 27