2020 Q1 and Q2 Construction Timeline (as of March 13, 2020)

COMPLETED – December 16 – January 24: Completion of ramp to the 15 Queens Quay East underground garage.

COMPLETED – January 13 – January 29: Road widening excavation & clean cap, along the northern section of the site adjacent Queens Quay East.

COMPLETED – February 1 – February 4: Construction of the pedestrian walkway adjacent 15 Queens Quay East.

COMPLETED – December 16 – March 13: Completion of the pedestrian link paving to the Waterfront Toronto Parking Lot, on the west side of 15 Queens Quay East.

March 7 : Reinstatement of Building D [29 Queens Quay East] Fire Route & Roundabout complete.

February 24 – March 18: Hoist [External construction elevator] removal from 15 Queens Quay East.

March 6 – May 31st: Commencement of remaining 15 Queens Quay East landscape work.

March 16 – March 30: New pavers and curbs installed for the Building D [29 Queens Quay East] Fire Route & Roundabout complete.

Spring 2020 – end of May: Reinstatement of Building D [29 Queens Quay East] Softscape (e.g. plantings). 

Landscape Plan for Q1 and Q2 work at Pier 27